Fort Liberty on the page, Fort Bragg in the paperwork
The Army renamed the post in 2023 and put the Bragg name back on February 14, 2025, this time honoring Pfc. Roland L. Bragg, per the Army's release. The old name stays in the headline so you can find this page. Everywhere else, we say Bragg.
This page is about the neighborhoods that touch the post: Spring Lake and the north side of Fayetteville, where the post and Pope Army Airfield sit, plus the Hoke and Harnett edges. The installation is federal land under the Army, so it has no town or county permit desk, and nothing here covers work inside the gates. For a lot outside the fence, start by asking which office governs the ground your slab will sit on. Our area page for the post covers the rest of the neighborhood.
Spring Lake, Fayetteville or the county: who signs off
Spring Lake's town limits take in parts of the post, and the town runs its own Inspections Department. Its page says every inspection has to be scheduled through the town office, not Cumberland County's, even though the county helps with some of them. Applications go through the town's online Customer Portal, which needs an account. The town has no full-time planning director, so zoning questions mostly land at county planning. Its pages don't spell out an apron rule, so call the Inspections Department before anyone sets forms.
Inside Fayetteville, the rules change. The city's driveway permit guide says an owner-occupied single-family home or duplex doesn't need the commercial permit; the residential one comes straight from the city, and a new curb cut needs the City Manager's approval. For the first 12 feet back from the street edge, a one-car garage lot tops out at 16 feet wide and a two-car or larger garage lot at 24. Unincorporated lots answer to county Planning & Inspections, which doesn't say online whether a pad needs a permit, so ask. The permit guide lines these offices up side by side.
Pours around the post are priced by the square foot, $7 to $12 per sq ft, and tearing out an old pad adds $1.50 to $4 per sq ft. Treat these sizes as examples, since your lot sets the real number.
| Job | Size | Per sq ft | What it comes to |
|---|---|---|---|
| Single-car strip, 16 feet wide | 16x40 (640 sq ft) | $7 to $12 | $4,480 to $7,680 |
| Two-car pad | 600 to 720 sq ft | $7 to $12 | $4,500 to $8,500 |
| Two-car pad, 24 feet wide | 24x30 (720 sq ft) | $7 to $12 | $5,040 to $8,640 |
| Rental pad between tenants | 18x30 (540 sq ft) | $7 to $12 | $3,780 to $6,480 |
| Tear-out and haul-off of that rental pad | 540 sq ft | $1.50 to $4 | $810 to $2,160 |
That's square-foot math and nothing more. Slope, truck access, thickness and the width your permit office allows all move the number. We give a free written estimate after we see the site.