County seat, two offices and one call to sort them
This is the Hoke County seat on US 401, so the courthouse and the permit offices sit in the same town. That helps, but it doesn't make the paperwork simple. The city lists a Code Administration department that covers code enforcement, planning, zoning and building inspections. The Hoke County Building Inspection Department handles building, electrical, mechanical, plumbing and insulation inspections on the county side.
County Planning runs zoning for unincorporated areas only, and the county ordinance leaves out land inside a municipality's extraterritorial area. Which counter gives a zoning permit for an in-city lot is a question for City Hall, so make that call before you pick a pour date. If the county handles your plans, review of a single-family house takes 1 to 3 working days, the county wants two sets of plans, and the permit cost doubles if work starts without the permit. Fort Bragg spans Cumberland County, Hoke County and Harnett County, so a lot on the post's edge answers to the office on its own side of the line. Our permits guide covers the Cumberland County side for comparison.
The Hoke County route for land outside the city
The rural side of the Raeford area, outside the city and its extraterritorial area, answers to the county. A homeowner there goes through three steps. Environmental Health comes first for septic, and a lot on public sewer skips it. Then the Planning Department issues a zoning permit, which asks that the lot meets the setbacks in the Zoning Ordinance and is not in the flood zone, wetlands or an easement. Last, Building Inspections issues the building permit. The county asks for a plot plan showing the lot, the buildings and the location and size of parking and driveways.
The ordinance says no land is used and no building put up, moved or structurally altered until a zoning permit is issued. The permit goes void if work hasn't started within 180 days. In a water-supply watershed a Watershed Protection Permit is also required. The RA-20 and R-20 districts need 20,000 sq ft lots, 80 feet of width, and setbacks of 30 feet front, 10 side and 25 rear. R-15 lots are 15,000 sq ft and R-8 lots are 8,000 sq ft at 70 feet wide. The ordinance was amended on September 2, 2025, so check the current table with Planning before a stake goes in.
Monolithic work runs $8 to $15 per sq ft. These sizes come straight from that range.
| Job | Size | Per sq ft | What it comes to |
|---|---|---|---|
| Detached shop or garage | 600 sq ft | $8 to $15 | $4,800 to $9,000 |
| Addition with thickened edge | 900 sq ft | $8 to $15 | $7,200 to $13,500 |
| Whole-house example | 1,200 sq ft | $8 to $15 | $9,600 to $18,000 |
| Large ranch plan | 1,500 sq ft | $8 to $15 | $12,000 to $22,500 |
Slope, fill, stone base, rebar and a stem wall change the total. Stem walls and footings are quoted per job. Every price is confirmed in a free written estimate after we see the site.