Faceville, Wagram and the Blaney slopes
Soil survey points read at 60 places inside the city came back Faceville loamy sand at 18 (two slope classes), Faceville-Urban land at 10, and Blaney loamy sand 8 to 15 percent slopes, Wagram loamy sand, Duplin sandy loam, Wagram-Urban land and Lakeland-Urban land at 4 each. NRCS rates Faceville and Wagram as well drained, and neither is limited for a house without a basement.
The ground drains, so concrete retaining walls in Raeford are about the footing and the cut, not about wet soil. The Blaney 8 to 15 percent slope spots are the ones to watch. Slope is where a retaining structure earns its keep. A yard with that much fall needs a bank held, a terrace made or a driveway cut into the hill. The NRCS ratings for the main soils in the city are good news for a footing, but a rating is an average. Your bank is one yard, and we confirm it with a probe.
Concrete retaining walls in Raeford: city lot or county lot? Start there
The City of Raeford lists a Code Administration department that covers code enforcement, planning, zoning and building inspections. Start at City Hall if your lot is inside city limits. Hoke County's courthouse and permit offices are in town too, so if your lot is out in rural Hoke or Rockfish under county jurisdiction, that's where you go for permits.
The county zoning ordinance applies to unincorporated land only, and it excludes land inside any municipality's extraterritorial area. If your lot is in the city, the county's setbacks are not your rules. Ask City Hall who issues the zoning permit and who inspects. If your lot is outside the city, the county's Zoning Permit page applies, and the county's Planning counter is the place to start. Either way, get the answer before you commit to a height, because the height sets the engineering and the price.
Not sure? Call City Hall with the address. They can tell you in a minute, and it saves a trip to the wrong counter. Ask who inspects the footing and the drain, too, since that decides when we schedule the pour. Our permit guide compares the offices around Fayetteville, including the City of Fayetteville, Cumberland County, the Town of Hope Mills and the Town of Spring Lake. Those towns run their own counters. Raeford's City Hall lists its own Code Administration, and Hoke County has its own desks, so a neighbor's permit story from another town won't match yours.
We price walls here by the square foot of face, $25 to $45 per sq ft, poured or block up to about 4 feet. Length times height gives you the face.
| Job | Size | Per sq ft of face | What it comes to |
|---|---|---|---|
| Garden terrace step | 15x4 ft (60 sq ft) | $25 to $45 | $1,500 to $2,700 |
| Bank at a corner-lot driveway | 36x3 ft (108 sq ft) | $25 to $45 | $2,700 to $4,860 |
| Terrace on a Blaney slope | 70x3 ft (210 sq ft) | $25 to $45 | $5,250 to $9,450 |
| Long rear bank | 100x3 ft (300 sq ft) | $25 to $45 | $7,500 to $13,500 |
| Over about 4 ft | Engineered | Per design | Priced after the drawings |
That's length times height times the range. Footing depth, fill, drain stone and access move the number. We give a free written estimate after we see the site.