Stedman has no permit counter: Cumberland County does it all
The Town of Stedman's own website says Cumberland County provides planning and inspection services: all permitting, planning, zoning, code enforcement and mapping, plus tax collection. Stedman Town Hall isn't where you file. Your application goes to the county's Building Inspections & Permitting office in Fayetteville, and the county's zoning staff prepared the town's zoning ordinance in the first place.
That ordinance, effective in 1987 and reprinted with amendments through 2015, requires a zoning permit from the Zoning Inspector before excavation or construction of any building or structure, accessory ones included. Permits go void after six months without real progress. The Town of Spring Lake and the Town of Hope Mills run their own inspection desks, but Stedman has none. Your first move is a call to the county with the parcel number, then a quick read of our permit guide so you know which questions to ask.
The county permit office works out of the Historic Courthouse in Fayetteville, and the county's inspections page is the place to start. Town Hall handles town business; the application itself goes to the county.
Accessory buildings, lot lines and where a pad can go
If your slab sits under a shed, a storage shop or a utility building, Section 7.28 of the Stedman ordinance sets the placement. An accessory building can't go in a required front or side yard, can't sit within 15 feet of a side street line, must stay 5 feet from a lot line that isn't a street line and 5 feet from another building, and can't be closer to the street than the principal building.
Those rules are easy to miss when the plan is just a sketch. A pad that gets drawn 3 feet off the back line can't legally carry a building, and you'd be tearing out concrete to fix it. Bring a survey or a plat to the site visit, and we'll measure the setbacks off it before the forms go in. Ask the county whether your entrance needs its own permit too.
Flatwork runs $8 to $14 per sq ft for a reinforced 5 to 6 inch slab, priced per job after a site visit. These sizes multiply out from that range.
| Job | Size | Per sq ft | What it comes to |
|---|---|---|---|
| Dumpster pad | 10x10 (100 sq ft) | $8 to $14 | $800 to $1,400 |
| Churchyard or shop walk | 4x100 (400 sq ft) | $8 to $14 | $3,200 to $5,600 |
| Equipment pad | 20x30 (600 sq ft) | $8 to $14 | $4,800 to $8,400 |
| Shop floor slab | 40x60 (2,400 sq ft) | $8 to $14 | $19,200 to $33,600 |
Extra stone on wet ground, floodplain grading, the NCDOT wait and tear-out of an old pad can move a Stedman total. Every price is confirmed in a free written estimate after we see the site.